We have some very important construction updates that will affect everyone beginning after we return from Spring Break. Below is an aerial view graphic, however please be sure to scroll down to the bottom of the newsletter to read up on these updates and view the simulation video of what kiss and ride, buses at dismissal, and parking will look like.
**UPDATED/NEW INFORMATION**
- Visible activity will begin Monday, April 3rd (Spring Break)
- Rear parking lot will no longer be accessible after March 31st
- ALL faculty and staff will have a parking spot in main parking lot
- 45 additional parking spots are being added during Spring Break
- Paid student parking will be along the fence line and on Peace Valley
- Additional reserved spots will be added on Peace Valley
- One way in, one way out for all vehicles will go into effect following Spring Break
- Buses will line up in two separate aisles at dismissal
- Kiss and ride will move to front parking lot
- Student crosswalk will be extended
Link to Video Simulation - Justice HS Bus Loop (3.16.2023).avi